CENAL ELEKTRİK ÜRETİM A.Ş. – Turkey

Karabiga/Biga, Turkey .  Power Plant Performance Acceptance Test .  Karabiga/Biga, Turkey

Karabiga/Biga, Turkey
Power Plant Performance Acceptance Test
Karabiga/Biga, Turkey

Total Power 1320MW

ASME PTC46, ASME PTC 4, ASME PTC 6

TGPS is executing the power plant performance acceptance test for the project Karabiga Thermal Power Plant.

The project description includes two blocks of 660MW each using ultra-super critical boiler technology from Alstom. This is the first 2x660MW ultra-supercritical boilers to be installed in Turkey.

The testing program includes the following activities

• Revision of the performance, emissions and acoustic guarantees.
• Revision of the design of the plant and current instrumentation.
• Revision of the performance test procedure.
• Creation of the emissions and acoustic test procedures
• Approval and applicable revisions of the performance, emissions and acoustic test procedures until they are accepted by all the involved parties.
• Supply high-precision temporary testing instrumentation to conduct the overall plant performance tests.
• Installation of the precision testing instrumentation.
• Technical Direction during the performance test (thermal, emissions and acoustic testing)
• Collection of data from all available resources (high-precision instrumentation)
• Creation of the preliminary performance test report
• Creation of the final performance test report
• Discussion of testing results with the witnessing party until acceptance

Why is Power Plant Efficiency Important?

Power Plant Efficiency is directly correlated to the business sustainability in terms of financial performance and long-term feasibility.