Red Eléctrica de España

Red Eléctrica de España ENDESA Gran Canarias

Red Eléctrica de España ENDESA Gran Canarias

1,500MW

Baleares

3,600MW

Ceuta & Melilla

150MW

Total Power: 5,200MW

 

ASME PTC 46, ASME PTC 22, ASME PTC 6, ASME PTC 4, ASME PTC 17

TGPS has been hired by the grid operator, Red Electrica de España to supervise the execution of the test to determine the generation costs and start-up costs of 87 power plants around the islands of: Tenerife, Gran Canaria, Lanzarote, Ceuta, El Hierro, La Gomera, Palma de Mallorca and Ibiza.

In total the following number of plants are to be tested during 18 months period.

Performance testing to regulate the electrical systems in the islands.

Tests: 87

  • Combined Cycles: 9
  • Diesel: 43
  • Gas Turbine: 28
  • Steam Turbine: 5
  • Coal Plants: 2

The goal is to understand the generation costs of each plant to review the electricity prices.